Production planning and Control
department is one of the important department for the apparel manufacturing
company. In the context of the apparel manufacturing primary roles of the
Production Planning and Control (PPC) department has been listed below. Each
functions has been explained briefly just overview about the task.
Job or Task Scheduling: Preparation of time and action calendar for each order from
order receiving to shipment. The job schedule contains list of tasks to be
processed for the styles. Against each tasks planner mentions when to start a
task and what is dead line for that task. Name of responsible person
(department) for the job is being listed. For example, scheduling planned cut
date (PCD), line loading date etc.
Material Resource Planning (Inventory):
Preparation of Material
requirement sheet according to sample product and buyer specification sheet.
Consumption of material (fabric, thread, button, and twill tape) is calculated
and estimated cost of each material.
Loading production: Planner defines which style to be loaded to the production
line and how much quantity to be loaded.
Process selection & planning: Processes needed to complete an order vary style to style.
According to the order (customer) requirement PPC department select processes
for the orders. Sometime extra processes are eliminated to reduce cost of
production.
Facility location: Where a company has multiple factories (facilities) for
production and factories are set for specific product, planner need to identify
which facility will be most suitable for new orders. Sometimes there may be a
capacity shortage in a factory, in that case planner need to decide which
facility will selected for that orders.
Estimating quantity and costs of
production: Planner estimate daily production
(units) according to the styles work content. With the estimated production
figure, production runs and manpower involvement planner also estimate
production cost per pieces.
Capacity planning: PPC department plays a major role during order booking.
They decide (suggest) how much order they should accept according to their
production capacity. Allocating of total capacity or deciding how much capacity
to be used for an order out of total factory capacity. Regularly updating
factories current capacity (production capacity).
Line planning: Preparing detailed line planning with daily production
target for the production line. Most cases line planning is made after
discussing with production team and Industrial engineers.
Follow up and execution: Whatever plan is made is executed by PPC department. PPC
department keeps close look whether everything is progressing according the
plan. Chasing other department heads on daily basis to keep plan on track. They
update order wise completed tasks on the Time & action Calendar. When
they found something is going to be late they expedite and create an alarm
about the delay.
No comments: