In “Line loading plan” planner
decides on which date a style to be loaded and how many lines to be considered
for the style to meet the production completion date. Line loading plan is an
important task for a production planner. Planner needs to do backward and
forward planning based on lead time. In this article I will explain how to make
line loading plan and what things are important during making a loading plan.
Explanation is given step by step in the following with examples. There is lot
of mathematical calculation. So, I will suggest you to use spread sheet for the
making the plan.
Step 1: Make a list of current orders with details such as order
no., order quantity, style description, and production completion date. Refer
to the Table-1. Suppose order has been received on the month March and
production completion date on May from 4th to 21st.
Table- 1: Order list
Order No.
|
Garment
Description
|
Order
Quantity
(pieces)
|
Production
completion date
|
OCS101
|
Dress
|
2000
|
10th May
|
OCS102
|
Blouse
|
3000
|
12th May
|
OCS103
|
Trouser
|
5000
|
15th May
|
GAP104
|
Long
sleeve Tee
|
3000
|
17th May
|
GAP105
|
Skirt
|
3000
|
21st May
|
GAP106
|
Dress
|
1500
|
21st May
|
GAP107
|
Long
sleeve Tee
|
10000
|
10th May
|
GAP108
|
Skirt
|
1200
|
04th May
|
Total
|
28,000
|
Step 2: Suppose a factory has 5 production lines. Calculate
available capacity of the line using capacity calculation formula considering
absenteeism (10%) and line. You should have knowledge about line wise
production efficiency to calculate actual capacity of a line. Or calculate it
prior to line loading plan.
Available capacity in hours = {(No. of operators/machines x working days in a
month x daily work hours x 60) – absenteeism %} x Efficiency %
Line wise available capacity has
been shown in the Table-2. It is considered that each line is equipped with
25-32 machines (operators), factory’s normal shift time is 8 hours (480
minutes) and line efficiency is in the range of 39% to 55%.
Table- 2: Available capacity
calculation
Line No.
|
No. of
Operator
|
Minutes/Day
(Daily
working Hrs. X 60)
|
Line
Efficiency
|
Absenteeism
%
|
Capacity
available
|
Line 1
|
30
|
480
|
40%
|
10%
|
5184.0
|
Line 2
|
28
|
480
|
50%
|
10%
|
6048.0
|
Line 3
|
32
|
480
|
55%
|
10%
|
7603.2
|
Line 4
|
32
|
480
|
45%
|
10%
|
6220.8
|
Line 5
|
25
|
480
|
39%
|
10%
|
4212.0
|
Step 3: Next, calculate required capacity for each order (style) in
minutes and in days. Assume that above 8 styles to be run in 5 lines and styles
will be loaded only in single line. Consider that all lines blank and you have
no issue with starting date. In this stage you have to also decide which line
to be chosen for the styles. Allocate order to the line according to product
category and line set up (machines laid). In Table-3 line number has been
mentioned against the order number. Use the following formula for the
calculation.
Capacity required in minutes = Order
Quantity X Style SMV
Capacity required in days = Capacity
required in minutes / Capacity available per day.
Refer to the table-3 for calculated
minutes and days required for each style.
Table-3: Required capacity
calculation
Order No.
|
Loaded to
Line No.
|
Order
Quantity
|
Style SMV
|
Capacity
Required (Minutes)
|
Capacity
available per day
|
Capacity
Required (Days)
|
OCS101
|
Line-1
|
2000
|
28
|
56000
|
5184
|
11
|
OCS102
|
Line-2
|
3000
|
25
|
75000
|
6048
|
12
|
OCS103
|
Line-3
|
5000
|
20
|
100000
|
7603.2
|
13
|
GAP104
|
Line-4
|
3000
|
10
|
30000
|
6220.8
|
5
|
GAP105
|
Line-5
|
3000
|
18
|
54000
|
4212
|
13
|
GAP106
|
Line-1
|
1500
|
28
|
42000
|
5184
|
8
|
GAP107
|
Line-4
|
10000
|
10
|
100000
|
6220.8
|
16
|
GAP108
|
Line-5
|
1200
|
18
|
21600
|
4212
|
5
|
Step 4: Now do backward calculation to find the date for style
loading. Days needed to complete production on due date, Sundays and holidays
must be excluded in day count. And add one to two days initially for line
setting according to style requirement. If required, you can add buffer
for one to two days. To make it easy in calculating the loading dates
considering above points use spreadsheet based planning board. For example
refer to the following image-1. I have made loading plan on the planning board
for theses styles. Light blue colored columns represent Sunday (weekly off
days). Finally make another table (Table-4) representing loading date
against orders.
Table-4: Order loading date
Order No.
|
Garment
Description
|
Loaded to
Line #
|
Production
completion date
|
Capacity
Required (Days)
|
Loading
date
|
Comments
|
OCS101
|
Dress
|
Line-1
|
10th May
|
11
|
26th April
|
|
OCS102
|
Blouse
|
Line-2
|
12th May
|
12
|
27th April
|
|
OCS103
|
Trouser
|
Line-3
|
15th May
|
13
|
28th April
|
|
GAP104
|
Long
sleeve Tee
|
Line-4
|
17th May
|
5
|
11th May
|
|
GAP105
|
Skirt
|
Line-5
|
21st May
|
13
|
5th May
|
|
GAP106
|
Dress
|
Line-1
|
21st May
|
8
|
11th May
|
|
GAP107
|
Long
sleeve Tee
|
Line-4
|
10th May
|
16
|
21st April
|
|
GAP108
|
Skirt
|
Line-5
|
04th May
|
5
|
28th April
|
Step 5: Once you gone through this article, practice this with some
of your real styles. I wish you can make it. If you feel you need further
assistance then write us?